就某矿山项目采用的地源热泵冷热源方案,分别从常规能源替代量、环保效益、经济效益等方面做了预评价,结果认为,与常规供暖、空调方式相比,地源热泵系统环保效益好,经济效益一般,增量投资回收期小于10年,方案可行。
On view of ground source heat pump design in a mine project, the pre-evaluation is carried out respectively from the conventional energy substitute, environmental benefits, and economic benefits, etc. The evaluation results show that compared with conventional heating and air-conditioning mode, groundsource heat pump system has better environmental benefits, but economic benefits is ordinary, the incremental investment payback period is less than 10 years, and then the project is feasible.
出处
《有色冶金节能》
2016年第3期49-53,共5页
Energy Saving of Nonferrous Metallurgy
关键词
地源热泵系统
环保效益
经济效益
预评价
ground-source heat pump system
environmental benefits
economic benefikts