对核电厂在调试阶段的现场隔离与隔离钥匙进行详细介绍,并对调试现场隔离与隔离钥匙的管理进行了说明,通过对调试阶段的现场隔离与隔离钥匙的详细介绍,对调试阶段的现场隔离与隔离钥匙有一定的了解,对核电厂调试阶段的现场隔离与隔离钥匙的应用有一定的理解,对调试阶段的相应的工作流程中涉及隔离钥匙有一定的介绍,同时也对此相应负责人的审核进行了详细的说明,对各种调试工作中涉及隔离钥匙有一定的借鉴意义,通过对此管理规定的了解,为以后对核电厂调试阶段的相应工作有一定的参考意义,为保证核电厂调试阶段工作的安全,为核电厂的经济性和安全性做出贡献。
Of nuclear power plant in the debugging phase isolation and isolate the key field in detail, and isolated with keys for debugging site management illustrates, through to the commissioning stage site isolation and isolate the key details, site isolation and isolate the key to debugging stage have a certain understanding, site isolation and the isolation of the key stage of nuclear power plant debugging applications have a certain understanding, involved in the process of debugging phase of the corresponding work has certain isolation key introduces, at the same time corresponding to this, head of the audit has carried on the detailed instructions, for a variety of debugging work involved in isolation keys have certain reference significance, through the provisions on the administration of understanding, to the nuclear power plant debugging for later stage of the corresponding work has certain reference value, in order to guarantee the safety of the nuclear power plant debugging stage work, contribute to the economy and safety of nuclear power plants.
出处
《科技视界》
2016年第15期250-250,269,共2页
Science & Technology Vision
关键词
隔离钥匙
发放
回收
归还
Isolate the key
Issue
Recycling
The return