摘要
板涧河调蓄水库大坝工程坝型为混凝土面板堆石坝,坝体填筑期施工强度大、难度高,同时面临上游跨趾板运输的施工难题,文中按照工期要求、施工强度科学合理地规划石料场、利用溢洪道石方开挖料,修筑上下游施工道路进行大坝填筑。
The dam of the Banjianhe River Regulating Reservoir is concrete faced rockfill dam. The construction is high in intensity and difficulty during dam body filling. Transport across toe board upstream is difficult in construction.Reasonable quarry planning was made in this paper according to construction time requirements and construction intensity. Excavation material obtained from spillway construction was used to construct the construction road upstream and downstream so as to fill the dam body.
出处
《山西水利科技》
2016年第1期30-31,34,共3页
Shanxi Hydrotechnics
关键词
面板堆石坝
工期
施工道路布置
料场规划
concrete faced rockfill dam
construction period
construction road arrangement
stock ground planning