期刊文献+

10kV混合线路重合闸投退原则探讨 被引量:3

Policy of the Reclosing Mode for 10 kV Mixed Lines
下载PDF
导出
摘要 随着城市化建设的推进,架空线路逐步被电缆线路所取代,势必会出现越来越多的电缆和架空混合线路。按各地调度规程的规定,全架空线路投自动重合闸;全电缆线路不投自动重合闸;但电缆和架空混合线路中重合闸的投退没有明确的规定。从电力系统的安全性和可靠性出发,通过分析各地混合线路重合闸投退原则的实例,综合考虑电缆的类型和敷设方式、运行时间等因素的影响,用ATP-EMTP仿真分析来计算电缆线路长度占全长线路的最佳比例,以此来确定重合闸的投退,提出一个比较合理的10kV混合线路重合闸投退原则。 With the development of city construction, overhead line is gradually replaced by cable conductor, and there will be more and more cable-overhead lines.According to provisions of all scheduling rules,for all overhead lines,auto-reclosing is adopted;for all cable lines,the auto-reclosing is unused.But the policy is not clearly defined on switching on or off of reclosing for hybrid lines of cable and overhead lines.From the view point of security and reliability of power system,by analyzing policies of reclosing for hybrid lines in different areas,and taking into account types,laying methods and running time of cable lines,switching on or off of reclosing is confirmed using the ATP-EMTP simulatiorl of the length proportion that cable lines account for whole lines.The more reasonable policy of switching on or off of reclosing is put forward for 10 kV hybrid lines.
出处 《山东电力技术》 2015年第11期47-51,共5页 Shandong Electric Power
关键词 混合线路 重合闸 投退原则 安全性 mixed lines reclosing the policy of switching on or off security
  • 相关文献

参考文献17

二级参考文献115

共引文献264

同被引文献43

引证文献3

二级引证文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部