摘要
文章根据我公司宁东能源重化工基地大型输水管道水锤防护工程实践,分析总结了采用单向调压塔和箱式双向调压塔进行水锤防护及实际情况,提出了大管径高扬程输水管道水锤防护及优化方案,供同类工程参考。
In the paper, according to the large pipes for water hammer protection engineering practice in our company's Ningdong energy heavy chemical base, analysis and summarize the water hammer protection and the actual situation of using one-way surge tower and box-type two-way surge tower, put forward the water hammer protection and the optimization solution in high-lift and large diameter water transmission pipeline, and it can be referenced for similar projects.
出处
《广东化工》
CAS
2015年第23期93-96,105,共5页
Guangdong Chemical Industry
关键词
调压塔
水锤防护
大管径
高扬程
surge tower
water hammer protection
largediameter
high-lift