结合工程实践,就CNG加气站施工过程中的预留设计偏差、设备尺寸参数偏差以及施工现场统筹管理中存在的问题进行分析,提出相关措施。
Combined with an engineering practice ,the reserved design errors and parameter errors of equipment size during construction of a CNG refileling station and problems existing in coordination management of construction site are analyzed, and the corresponding measures are put forward.