摘要
对长城六矿由立井一期工程转入巷道二期工程施工期间的工序快速转换和保障施工安全的临时系统建设过程中所采取的技术管理措施作了阐述。该矿采取了一系列科学合理的施工技术和管理措施,确保了现场施工工序转换和衔接工作安全顺利进行,取得了良好的技术经济效果。
During an establishing process of the procedure rapid conversion and construction safety pro‐tection interim system from the period of mine shaft first phase of Changcheng No.6 Mine to the mine roadway second phase construction ,the technical management measures conducted were stated. A series of the scientific and rational construction technology and management measures conducted in the mine could ensure the site construction procedure conversion and connection works safely and success‐fully conducted and good technical and economic benefits were obtained.
出处
《建井技术》
2015年第3期1-3,共3页
Mine Construction Technology
关键词
基建矿井
生产系统
临时改绞
工序转换
construction mine
production system
interim winch changed
procedure conversion