摘要 以宝业·万华城项目23号楼标准户型的施工为研究对象,对施工过程中存在的问题进行梳理,提出相应的措施,整个项目施工的应用结果表明这些措施是行之有效的。装配式建筑施工不同于传统全现浇建筑施工,在设计阶段应充分考虑施工时各工序对预制构件的影响,管理人员及作业人员宜全面掌握相关的专项施工技术,避免因操作不到位而导致的安装误差。 Taking Baoye·Wanhuacheng No. 23 standard apartment as the research object,problems existing in the real process of construction are analyzed,the corresponding countermeasures are put forward,and the results of application of the whole project show that these measures are effective. Precast construction is different from traditional cast-in-place construction. In design stage,the influence of the construction process on the prefabricated components should be fully considered. Managers and operating personnel ought to master the specific construction technology involved,in order to avoid the mistakes caused by the inappropriate operation of the installation.
出处 《施工技术》 CAS 北大核心 2015年第16期57-59,共3页 Construction Technology
关键词 预制装配式 叠合板式混凝土剪力墙结构 预制构件 施工技术 precast composite slab concrete shear wall structure precast element construction
  • 相关文献

参考文献7

  • 1中国建筑标准设计研究院,中国建筑科学研究院.JGJ1-2014装配式混凝土结构技术规程[s].北京:中国建筑工业出版社.2014. 被引量:4
  • 2安徽建筑工业学院.DB34810—2008叠合板式混凝土剪力墙结构技术规程[S].合肥,2008. 被引量:1
  • 3安微省建筑科学研究设计院_ DB34/T1468—2011叠合板式混凝土剪力墙结构施工及验收规程[S].合肥:安徽省工程建设标准设计办公室,2011. 被引量:1
  • 4国务院办公厅.国办发〔2013〕1号关于转发发展改革委住房城乡建设部绿色建筑行动方案的通知[R]. 2013. 被引量:1
  • 5浙江省人民政府办公厅.浙政办发〔2012〕152号关于推进新型建筑工业化的意见[R]. 2012. 被引量:1
  • 6上海市人民政府办公厅_沪府办〔2013〕52号关于本市进一步推进装配式建筑发展若干意见的通知[R]. 2013. 被引量:1
  • 7江苏省人民政府.苏政发〔2014〕111号关于加快推进建筑产业现代化促进建筑产业转型升级的意见[R]. 2014. 被引量:1

共引文献3