长期浸水对未完工隧洞围岩及衬砌结构的影响

Impacts on Surrounding Rock and Lining of Uncompleted Tunnel Immersed in a Long Term
下载PDF
导出
摘要 新疆某无压输水隧洞饱和水土体洞段在未完工的情况下被水长时间浸泡,造成围岩二次加速变形,通过浸水前后收敛变形数据反演土体物理力学参数,并对隧洞衬砌结构内力及配筋结果进行对比验算。 The uncompleted and saturated section of one pressure-free water transmission tunnel in Xinjiang is immersed in a long term. This causes a secondary expediting deformation of the surrounding rock. Through the data of convergence and deformation of the surround- ing rock before and after being immersed, the physical-mechanics parameters of the soil mass are derived in inversion. Meanwhile, the internal forces and reinforcement arrangement of the tunnel lining are compared and verified.
作者 冉建西
出处 《西北水电》 2015年第4期46-48,共3页 Northwest Hydropower
关键词 长期浸水 无压输水隧洞 饱和水土体 围岩变形 反演计算 衬砌内力. long-term immersion pressure-free water transmission tunnel deformation of surrounding rock inversion calculation internal force of lining
  • 相关文献

二级参考文献14

共引文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部