摘要
文章介绍巢湖供电公司10k V母线单相接地故障处理流程,分析影响故障处理时间的原因。通过添加特征响铃、建立虚遥信、实现异机监护等技术手段,使调度自动化系统在巢湖公司得到创新性的改进,缩短调控员在调控一体化模式下处理10k V母线单相接地故障时间,提高设备正常运行效率。
The workflow of 10kV bus phase-to-ground fault detection in the Chaohu Power Supply Company is introduced , the reason of affecting the fault processing time is analyzed .The dispatching auto-mation system is improved for the first time in the Chaohu Power Supply Company by special alerts , virtu-al remote signals and wardship on the other machine , to shorten the time of dealing with the failure in the model of dispatching and control integration , to improve the efficiency of normal operation of equipment .
出处
《安徽电气工程职业技术学院学报》
2015年第A01期59-61,共3页
Journal of Anhui Electrical Engineering Professional Technique College
关键词
自动化
调控一体化
单相接地故障
automation
dispatching and control integration
phase-to-ground fault