摘要
某工程桩基设计为预应力管桩,数量多、工期紧,地质条件复杂,如何保证施工质量和施工进度,即满足设计要求,又能满足业主和监理单位的要求,成为施工单位必须面对的问题。为此本工程严格按照现行施工规范及相应技术规程并结合施工现场条件进行施工,按照桩位确定、桩机就位、桩架调整、喂桩、沉桩(记录)、送桩、回油移桩机的施工工艺流程,确保了工程按质按量顺利完工。
The construction of a building in Xuancheng city is pre-stressed pipe piles. In order both to ensure the building quality and the schedule and to meet the need of the plan,the house owner and the supervisory organization, the construction unit must be faced with the problems of many pre-stressed pipe piles, complex geological conditions and tight schedule. However the construction unit strictly follows the current civil construction specifications and some related technical regulations as well as the building site conditions. The following are the technical procedures: the location of the piles→the fixing of static pile drivers→ the regulation of the pile rams →the placement of the piles →the sinking of the plies →observation of the recording→the oil shifting of the plies.Thus the building construction has been completed timely in good quality.
出处
《西昌学院学报(自然科学版)》
2015年第2期35-38,共4页
Journal of Xichang University(Natural Science Edition)
关键词
管桩
静压
质量控制
pipe piles
static pressure
quality control