以准朔铁路某梁场为例,介绍了吊移梁梁场布局和施工要点,并通过与滑移工艺的技术经济对比,说明了吊移梁技术的优点,为其他工程采用吊移梁技术提供了借鉴。
Take a certain precast in Zhun-Shuo railway for example,introduced layout and construction points of the precast beam field using hanging and shifting. By compaired with the slipping technology about economy and technology,illustrate the advantages of hanging and shifting technology,provided a reference for other project that using hanging and shifting technology.
出处
《山西建筑》
2015年第19期97-98,共2页
Shanxi Architecture
关键词
滑移方案
提梁方案
施工工艺
slipping solution
the program of lifting beam