摘要
本文介绍了660MW超超临界机组汽机房布置特点,总结了汽机专业施工图优化设计成果及施工调试阶段出现的典型问题。通过优化设计共节省材料成本487.1万元。
This paper introduces 660 MW ultra-supercritical unit turbine house arrangement and summarizes construction drawing optimal design of the steam turbine and the typical problems during the construction and debugging stage.4.871 million yuan of material cost is saved by the optimal design.
出处
《价值工程》
2015年第14期101-103,共3页
Value Engineering
关键词
超超临界机组
施工图
优化设计
ultra-supercritical unit
construction drawing
optimization design