本文以江都北路延伸工程古运河大桥为例,讲述了PC连续刚构桥施工监控全过程,通过对大桥线形和应力的监控,保证了大桥的施工安全和质量。
Taking the ancient canal bridge of Jiangdu north road extension project as an example,this paper introduced the whole monitoring process of the PC continuous rigid frame bridge construction,through the monitoring of the bridge alignment and stress,ensured the construction safety and quality of the bridge.
出处
《河南科技》
2015年第2期119-121,共3页
Henan Science and Technology
关键词
PC连续刚构桥
施工监控
线形
应力
PC continuous rigid frame bridge
construction monitoring
alignment
stress