摘要
母杜柴登煤矿二期工程施工初期,在不具备后配套连续运输的条件下,布置简易储矸转载系统,解决了悬臂式掘进机快速掘进与电机车牵引矿车间断运输不匹配的技术难题,提高了巷道施工进度,取得了月进尺达180~235m的好成绩。简易储矸转载系统除可与悬臂式掘进机配套使用外,还可与连采机、掘锚机等机掘设备配套使用,具有推广应用价值。
At an initial construction period of the second phase engineering of Mudu Chaideng Coal Mine,under a condition with no back supporting continuous transportation,a simple coal refuse storage and stage loading system was arranged to solve a mismatching technical problem between the rapid driving of the mine boom type roadheader and the discontinuous transportation of the mine cars hauled by the mine electric locomotive.The mine gateway construction schedule was improved and a month driving rate reached an excellent achievement of 180~235m.The simple coal refuse storage and stage loading system could not only be matched with boom type roadheader,but also could be matched with the continuous miner,driving an bolting machine and other mechanized equipment.The simple coal refuse storage and stage loading system could have the promoted and application value.
出处
《建井技术》
2014年第6期54-56,共3页
Mine Construction Technology
关键词
简易储矸转载系统
综掘施工
快速掘进
间断运输
simple coal refuse storage and stage loading system
fully mechanized mine gateway driving construction
rapid driving
discontinuous transportation