结合紧水滩水电厂梯级水库联合调度的运行实践,提出了做好水库调度基础工作、减少弃水、提高发电水头、抓好设备技术改造、合理利用超蓄等提高梯级电站综合效益的途径。
The joint operation of cascade reservoirs in Jinshuitan Hydropower Station is introduced. Experiences that could improve the overall benefit of such cascade stations are summarized,including the fundamental regulation work of cascade reservoirs,reducing the surplus water,increasing the power generating water head,technical renovation of equipment,and reasonable utilization of the surcharge capacity.
出处
《水电与新能源》
2015年第2期17-19,共3页
Hydropower and New Energy
关键词
梯级水库
联合调度
分期控制
综合效益
cascade reservoirs; joint operation; seasonal control; overall benefit