摘要
通过分析西安铁路枢纽现状及存在主要问题,结合西安铁路枢纽总图规划以及枢纽内既有货运设施和既有货运北环线的运输能力,比选分析零口、栎阳、相桥设直通场的方案。货车第二双线引入枢纽后,结合枢纽生产力布局,综合工程实施和工程投资因素,推荐新建货运第二双线栎阳车站设直通场方案。
In view of the current situations of Xi’an railway hub and existing main problems, this paper analyzes the plan to set up through-yard in Lingkou, Leyang and Xiangqiao stations with reference to the overall planning of Xi’an railway hub, the existing freight facilities and the capacity of the existing north circular line. According to the hub productivity distribution and other factors such as engineering implementation and project investment, it is proposed to set up a through-yard in Leyang station.
出处
《铁道标准设计》
北大核心
2015年第3期17-22,共6页
Railway Standard Design
关键词
铁路
西安枢纽
货运第二双线
直通场
方案研究
Railway
Xi’an railway hub
Second freight double line
Through yard
Program study