抬升法在房屋纠偏加固处理中的应用 被引量:2

Application of lifting method in deviation-rectifying and reinforcing treatment of building
下载PDF
导出
摘要 介绍了某6层框架剪力墙结构房屋抬升法纠偏的整个过程。通过在地基压入锚杆静压桩提供反力,在筏板上植筋架设反力梁,在桩顶设置千斤顶,辅助地下车库堆载加压的抬升纠偏方法,成功地完成了房屋的纠偏,使得房屋的倾斜率由5.5‰变为2‰以内。在纠偏全过程采用高精度测量机器人实时跟踪监测筏板基础的沉降值,是房屋成功纠偏的保证。 The whole deviation-rectifying and reinforcing treatment process of a 6-story framework shear wall structure building was introduced in this papaer.As counterforce is generated by installing anchored static-pressure piles in the foundation,counter-force beams and jacks are set respectively at the embedded steel bars of the raft and at the pile tips,so as to heap loading on the underground garage and coordinate the pressure against it.Thanks to such treatment,the leaning ratio of the building declined from5.5‰ to 2‰.High-accuracy measuring robot is used to monitor the settlement of the raft,which stands as the key to the success of the deviation-rectifying and reinforcing treatment of the building.
出处 《铁道建筑》 北大核心 2015年第1期67-70,共4页 Railway Engineering
基金 中国铁道科学研究院院基金(1451ZD2604)
关键词 纠偏加固 抬升法 堆载加压法 锚杆静压桩 Deviation-rectifying and reinforcing treatment Lifting method Heaping load for pressure Anchored static-pressure pile
  • 相关文献

参考文献8

  • 1唐业清主编..建筑特种工程新技术[M].北京:中国建筑工业出版社,2013:552.
  • 2唐业清.建筑物移位纠倾与增层改造[M].北京:中国建筑工业出版社,2008:356-420. 被引量:10
  • 3中华人民共和国住房和城乡建设部.GB50007--2011建筑地基基础设计规范[S].北京:中国建筑工业出版社.2011. 被引量:4
  • 4中华人民共和国住房和城乡建设部.JGJ270-2012建筑物倾斜纠偏技术规程[S].北京:中国建筑工业出版社,2012. 被引量:2
  • 5李启民,何新东,王桢等编著..建筑物纠倾工程设计与施工[M].北京:中国建筑工业出版社,2012:437.
  • 6郭子珍,侯东亚,尤相骏,濮久武.远程无线遥控测量机器人变形监测系统及其应用[J].测绘通报,2008(7):71-72. 被引量:6
  • 7练操,范萌,陈长军.基于测量机器人的远程遥控技术开发[J].人民长江,2011,42(22):89-91. 被引量:4
  • 8徐忠阳等编著..全站仪原理与应用[M].北京:解放军出版社,2003:209.

二级参考文献6

共引文献20

同被引文献18

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部