摘要 考虑到枕头坝一级水电站施工场内交通与施工进度、施工布置、施工料场等方面之间的密切关系,结合交通规划布置的原则与标准,对场内施工材料的运输流向及强度进行了分析,重点阐述了施工场内交通规划布置方案。工程实践表明,该方案满足施工高峰期运输要求,道路桥梁布置合理,车辆通行安全高效,为工程的建设及顺利投产奠定了坚实基础。 In consideration of the close relation between jobsite transportation for construction and construction schedule,construction layout and material yard,the transportation trend and intensity of jobsite construction materials were analyzed in combination with the principle and standard of traffic planning-layout,and the jobsite traffic planning-layout scheme was determined.The construction practice indicates that the road and bridge were arranged reasonably,the traffic scheme can fully satisfy the transportation demands in rush-hour,the vehicular traffic is safe and effective.It provides a solid foundation for engineering construction and operation.
出处 《人民长江》 北大核心 2014年第24期50-53,共4页 Yangtze River
关键词 施工布置 场内交通规划 安全高效 枕头坝一级水电站 construction layout jobsite transportation planning safety and efficient Zhentouba Ⅰ Hydropower Station
  • 相关文献

参考文献1

共引文献4

同被引文献18

引证文献7

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部