摘要
为防止武汉鹦鹉洲长江大桥2#桥墩建设对拟建的武桥水道航道整治工程建设和整治效果产生不利影响,提出将桥墩防护工程和其周边航道整治工程合二为一的设计方案,统筹安排施工进度,并根据建设过程中出现的问题,适时调整设计方案,解决了桥梁建设与航道整治工程之间的矛盾,确保两项工程保质、保量、按时竣工。
In order to prevent adverse effects of pier No. 2 of Yingwuzhou Yangtze River bridge on the waterway regulation engineering of Wuqiao waterway, we integrat the engineering of the bridge pier protection engineering and its surrounding waterway regulation engineering, arrange comprehensively the construction schedule, and adjust the design scheme timely according to the problems in the construction process to deal with the contradiction between the bridge construction and waterway regulation engineering, and ensure that the two projects complete on time and with high quality.
出处
《水运工程》
北大核心
2014年第12期142-146,共5页
Port & Waterway Engineering
关键词
鹦鹉洲大桥
桥墩防冲工程
航道整治工程
Yingwuzhou Yangtze River bridge
anti-scouring engineering for bridge pier
waterwayregulation engineering