达岱河水电站工程在施工过程中,通过研究分析工程地形地貌、地质条件、水文条件、以及施工进度计划,充分利用联通明渠,调整了主副坝度汛方案,减少了工程投资,降低了施工强度,确保了工程建设的推进。
During the construction of Tatay hydropower station, the project investment and the work intensity are greatly reduced through studying project topography, geological and hydrological conditions and construction schedule and adjusting flood passing scheme by making full use of open channel, which ensures the smooth progress of the pro-ject.