摘要
结合西安地铁1号线盾构区间的工程,通过始发前联系测量、始发测量、掘进测量和贯通测量4个工程阶段的测量详细阐述了地铁区间隧道盾构法的测量方法;同时分析了地铁区间隧道盾构法施工的技术参数、施工进度及过站方式等,可为以后西安地区地铁建设过程中盾构法施工的测量提供参考依据。
Combined with the construction of Subway Line 1 in Xi'an, survey technology for subway tunnel constructed with shield tunneling method was expounded including four stages of survey such as connection survey before launching, initial survey, survey while tunneling and survey after going through. Technical specifications, construction progress and the way how the shield tunneling machine passes the station were analyzed, which provides reference for later construction.