老挝南欧江五级水电站截流规划设计研究 被引量:1

Design of Closure Planning of Nanoujiang Stage-5 Hydropower Station
下载PDF
导出
摘要 为了实现老挝南欧江五级水电站顺利截流,结合南欧江五级水电站现场地形条件、水文、交通等因素,基于其施工导流采用分期导流的方式,分别从截流时段安排、截流标准、控制流量、截流方式、戗堤位置选择、龙口分区与控制、截流抛投材料、施工设备安排等方面进行了全面的截流规划设计,为实现老挝南欧江五级水电站顺利截流提供了技术保证。 In order to achieve river closure of Nanoujiang stage-5hydropower station in Laos successfully,considering the topography condition,hydrology condition,transportation condition on site at the station of the project,based on the stage river diversion adopted in the construction diversion of the project,a comprehensive river closure planning design was made from the aspect of closure period arrangement,closure standard,controlling flow,method of river closure,selection of closure dike location,closure gap section partition and controlling,material used in river closure and construction equipment arrangement.Thus,it provides technical assurance for river closure of Nanoujiang stage-5hydropower station in Laos successfully.
作者 张凌 王强
出处 《水电能源科学》 北大核心 2014年第11期93-96,132,共5页 Water Resources and Power
关键词 南欧江五级水电站 导流 截流 立堵 龙口 Nanoujiang stage-5hydropower station diversion river closure vertical closure closure gap
  • 相关文献

参考文献4

  • 1中国水电工程顾问集团公司,中国水电顾问集团西北测设计研究院,中国水电顾问集团昆明勘测设计研究院,等.水利水电工程施工组织设计规范(DL/T5397-2007)[M].北京:中国电力出版社,2008. 被引量:1
  • 2贺昌海,胡志根,周宜红,肖焕雄.立堵截流风险及其模型研究[J].武汉水利电力大学学报,1998,31(5):30-33. 被引量:15
  • 3肖焕雄编..施工水力学[M].北京:水利电力出版社,1992:212.
  • 4钟汉华,冷涛.水利水电丁程施工技术[M].北京:中国水利水电出版社,2010. 被引量:1

共引文献14

同被引文献5

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部