摘要
通过对电信政企客户机房现有交、直流供电系统存在的问题与安全隐患进行的分析总结,着重研究适合政企客户机房高可靠性的交、直流供电系统;并通过理论计算及工程实践,提出优化政企客户机房供电系统的可实施方案,同时设计出相应的交、直流供电系统优化示意图,以满足市场开发及政企客户对于通信运营商供电系统的安全、可靠、合理及适用性要求。
It analyzes the problems and security risk on the current AC and DC power supply system in customer equipment room, focus-es on the AC and DC power supply system suited to the high reliability of customer equipment room. Based on theoretical cal-culation and engineering practice, it presents the solution on optimizing customer equipment room power supply system, gives the optimization il ustration on the related AC and DC power supply system to meet the market development and the require-ments on safety, reliability, rationality and applicability of operators’power supply system.
出处
《邮电设计技术》
2014年第11期88-92,共5页
Designing Techniques of Posts and Telecommunications
关键词
政企客户
供电系统
优化
双电源
双总线
Government and enterprise customer Power supply system Optimization Duplicate power supply Dual bus