摘要
以某快速公交工程一号线车辆基地工程为例,通过研究该工程的特点、地质及水文条件,对该基坑进行了降水设计,主要对施工过程中发生的地下水管涌现象进行了分析,并探讨了具体的处理措施,为类似工程施工积累了经验。
Taking the vehicle base project along No. 1 Line of some express bus project as the example,the paper undertakes the dewatering design for its foundation pit,according to the features,geological and hydrological conditions,analyzes the underground water piping in the construction process,and explores factual treatment measures,so as to accumulate experience for the construction.
出处
《山西建筑》
2014年第33期60-62,共3页
Shanxi Architecture
关键词
管涌
基坑
地下水
地质
piping
foundation pit
underground water
geology