高桩承台加预应力锚索结构在长洲三线四线船闸中的应用 被引量:1

Application of elevated pile caps and prestressed anchor structures in the third line and the fourth line ship lock of Changzhou hydro-junction
下载PDF
导出
摘要 以长洲水利枢纽三线四线船闸为例,介绍了一种适用于受场地条件限制的新型导航墙结构——高桩承台+预应力锚索的复合结构。该结构通过高桩承台和预应力锚索的联合作用,有效地改善了桩基的内力条件,控制了结构的变形。在场地条件受到限制、使用荷载大、常用结构不适宜时,该结构具有较好的参考应用价值。 Taking the third line and the fourth line ship locks of Changzhou hydro-junction for example, this article presents a new navigation wall structure suitable for site conditions limited, namely the composite structure of elevated pile caps and prestressed anchor. This structure improves effectively the condition of the pile foundation internal forces and controls the deformation of the structure through jointing actions of elevated pile caps with the prestressed anchor. When the site conditions are limited, using loads are large and common structures are not appropriate.
作者 吴信 王大伟
出处 《水运工程》 北大核心 2014年第9期126-130,共5页 Port & Waterway Engineering
关键词 高桩承台 预应力锚索 导航墙 三线四线船闸 长洲水利枢纽 elevated pile cap prestressed anchor navigation wall the third line and the fourth line ship locks Changzhou hydro-junction
  • 相关文献

参考文献3

  • 1吴信.长洲水利枢纽三线四线船闸工程施工图设计[R].南宁:广西交通规划勘察设计研究院,2012. 被引量:1
  • 2聂庆科等著..深基坑双排桩支护结构设计理论与应用[M].北京:中国建筑工业出版社,2008:204.
  • 3何颐华,杨斌,金宝森,李瑞茹,谭永坚,王铁宏.双排护坡桩试验与计算的研究[J].建筑结构学报,1996,17(2):58-66. 被引量:216

共引文献215

同被引文献9

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部