水平定向钻孔-管直径比研究

Study on Borehole-Pipeline Diameter Ratio in Horizontal Directional Drilling
下载PDF
导出
摘要 在水平定向钻孔管道穿越施工时,需要适当增大扩孔直径来减小管道所受约束,这就要求确定合理的孔-管直径比。选取钻孔出土弯曲段作为研究对象,利用有限元仿真计算不同孔-管直径比条件下的管道应力分布以及回拖力变化,分析孔-管直径比最优选择。计算结果表明,孔-管直径比大于1.4时,管道最大应力值明显下降;孔-管直径比超过1.5时,管道最大应力趋于平稳。回拖载荷随孔-管直径比的增大而减小,且在孔-管直径比达到1.4后降幅逐渐减小,此时孔-管直径比对回拖载荷的影响减弱。综合考虑,孔-管直径比在1.4~1.5之间为最优。 Borehole reaming is often required to reduce the pipeline constraints when running pipeline through horizontal direetional borehole. Therefore, a reasonable borehole-pipeline diameter ratio needs to be deter- mined. Taking the unearthed curved section as the research object, the pipeline stress distribution and pullback force under different borehole-pipeline diameter ratio are calculated using the finite element simulation. The opti- mized borehole-pipeline diameter ratio is also analyzed. The calculation results show that, the pipeline maximum stress decreases significantly when the borehole-pipeline diameter ratio is greater than 1.4, and will become steady when the ratio exceed 1.5. The pullback load decreases with the increase of borehole-pipeline diameter ratio and the decreasing amplitude gradually decline as the ratio reaches 1.4. Meanwhile, the effect of borehole-pipeline diameter ratio on the pullback load weakened. As a result of overall consideration, 1.4 to 1.5 are the optimized borehole- pipeline diameter ratio.
出处 《石油机械》 北大核心 2014年第10期107-110,116,共5页 China Petroleum Machinery
基金 中石油管道建设课题"特殊地区管道建设关键技术研究"(2011B-3303)
关键词 水平定向钻 管道穿越 孔一管直径比 应力分布 回拖力 有限元分析 horizontal directional drilling borehole-pipeline diameter ratio stress distribution pullbackforce finite element analysis
  • 相关文献

参考文献10

二级参考文献25

共引文献46

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部