大直径深孔嗣后充填法采场结构优化的数值模拟 被引量:1

Numerical simulation on the Optimization of Stope Structure of Large-diameter Long Hole Afterwards Backfilling Mining Method
下载PDF
导出
摘要 针对新疆阿舍勒铜矿开采技术条件,采用Ansys有限元软件,对采场跨度为10,12,13,15 m时的围岩应力、位移变化规律进行了数值计算分析。结果显示,采场跨度是影响其稳定性的重要因素,在现有条件下,采场跨度在13 m以上是不稳定的,计算结果、相似模拟实验结果及开采实践对比分析表明,采场最佳跨度为8~12 m。 According to the mining technical conditions of Asele copper mine, the Ansys software is adopted to calculate and analyze the stress and displacement change rule of the stope wall rocks with various spans of 10,12,13,15 m. The research results show that,stope span is the important factor which influences the stability of stope. Under the existing condition, if the stope span is above 13 m, it will be not remain stable ,therefore,the optimal value of stope span is from 8 m to 12 m.
出处 《现代矿业》 CAS 2014年第7期6-9,共4页 Modern Mining
关键词 数值计算 采场结构优化 VCR法 Numerical calculation, Optimization of stope structure, VCR mining method
  • 相关文献

参考文献13

二级参考文献52

共引文献577

同被引文献10

引证文献1

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部