摘要
从广西电网电源接入系统方式存在的主要问题出发 ,研究了广西电网、南方电网的主要特点 ,提出在南方电网“西电东送”的形势下 ,电源接入系统应当考虑的问题和遵循的主要原则。在此基础上 ,研究了“十五”期间广西电源接入系统的方案。
Based on the problems from the configuration for connecting power sources in Guangxi power grid into the power system, by studying both the main characteristics of Guangxi and southern power grids and the situation of 'power transmission from west to east', the basic principle to be followed about the configuration for connecting power sources into the power system is presented. In addition, the plan for connecting power sources in Guangxi power grid into the power system within the 'tenth five-years' has been studied.
出处
《广西电力技术》
2002年第1期1-4,12,共5页
Guangxi Electric Power Technology
关键词
电网
电力系统
电源接入系统
优化
广西
power grid, power source, connecting into, power system