摘要
以工程实例为基础 ,重点阐述了抽水蓄能电站上水库渗漏、库岸稳定、输水线及地下厂房工程地质勘察研究的主要内容及有关主要工程地质问题的评价方法 .其次扼要地说明了已建上、下库坝工程地质勘察研究方法及天荒坪工程施工期 3 2 9滑坡的工程地质勘察 .
The article elaborates chief aspects of the engineering geological investigation about upper reservoir seepage,reservoir bank stability,water conveyance and underground powerhouse complex for pumped storage power station as well as appreciated method for relative engineering geological problems subsequently,it clarities briefly the engineering geological investigation for present upper and lower reservoir(dam) and for 3.29 land slip occurred at construction of TIANHUANGPING pumped storage project.
出处
《浙江水利水电专科学校学报》
2001年第4期1-10,共10页
Journal of Zhejiang Water Conservancy and Hydropower College
关键词
抽水蓄能电站
水库渗漏
库岸稳定
输水线
地下厂房
工程地质勘察
pumped storage power station
upper reservoir seepage
reservoir bank stability
water conveyance line
underground powerhouse
complex investigation