摘要
京珠高速公路广珠段 T线高架桥在软土地基上采用“满堂支架法”技术。叙述后张法预应力连续箱梁现浇施工中的合理施工方法和对工程难点所采取的技术措施。
“ Continuous trestle' construction technique was adopted in Jingzhu (Beijing─ Zhuhai) Express Highway, Guangzhu (Guangzhou─ Zhuhai) Section T- shaped trestle bridge project on soft foundation.The rational construction method adopted in in- situ casting of post- tensioned prestressed continuous box girder and technical measures taken for dealing with the difficulties of engineering are elaborated.
出处
《水运工程》
北大核心
2001年第2期35-38,50,共5页
Port & Waterway Engineering