摘要
比较了完全内桥接线变电所线备方式下和桥备方式下变电所全停的可能性,对照新的事故调查规程,提出了长桥变电所和里塘变电所运行方式的优化准备方案.
Comparison of the full stop possibility between line standby mode and bridge standby mode of internal bridge connection substation is made. Contrasting the new accident investigation procedures, Chang-qiao substation, Li-tang substation operation mode optimized preparation are put forward.
出处
《上海电力学院学报》
CAS
2014年第B04期47-50,共4页
Journal of Shanghai University of Electric Power
关键词
线备方式
桥备方式
优化准备
line standby mode
bridge standby mode
optimization preparation