资源约束网络进度计划模型研究

Study on resource-constrained network schedule model
下载PDF
导出
摘要 随着网络计划技术在工程中的广泛应用,人们发现传统的关键路线法(CPM)得出的时差和关键路线与工程实际有一定差别,其主要原因可归结为传统CPM假设资源不受约束,而实际工程中执行工序的资源有限,其使用要受到约束,因而传统CPM一般不能给出准确的时差和关键路线。通过研究,吸取资源约束RCS模型的优点,并引入了资源链,提出了改进的资源约束网络进度计划模型(IRCS模型),解决了资源约束与并行工序的问题,得出的网络进度计划时间参数更符合项目实际,有利于项目管理人员做出正确决策,对项目进度进行更有效的管理和控制。 As the network planning technology widely used in engineering, it is found that the float and critical path derived from the traditional critical path method (CPM) don't conform to actual project. The main reason can be attributed to the traditional CPM assumptions in which resources are unfettered, but resources are always constrained in actual project. Thus the traditional CPM generally can not give the accurate float and the critical path. This paper proposes an improved resource-constrained network schedule model (IRCS model). Having learned the advantages of resource constraints RCS model and the resource chain, the problems of constrained resource and parallel process is solved. The results are more in line with the actual project and will help managers to make the right decisions on the progress of project.
出处 《大坝与安全》 2013年第6期56-61,共6页 Dam & Safety
关键词 关键路线法(CPM) 资源约束 IRCS模型 资源链 critical path method resource-constrained IRCS model resource chain
  • 相关文献

参考文献9

  • 1王诺.网络计划技术及其拓广研究[M].北京:人民交通出版社,1998. 被引量:2
  • 2肖田元等编著..系统仿真导论[M].北京:清华大学出版社,2000:313.
  • 3Wiest J D. Some properties of schedules for large projects with limited resources[J]. Operation Research,1963,12: 395-418. 被引量:1
  • 4Gavish B, Pirkul H. Algorithms for multiresource general- ized assignment problem[J]. Management Science,1991,37 (6): 695-713. 被引量:1
  • 5Stinson J P. A branch and bound algorithm for a general class resource-constrained scheduling problem[D]. Univ. of North Carolina at Chapel Hill. Chapel Hill, N.C., 1976. 被引量:1
  • 6Lee J K, Kim Y D. Search heuristics for resource con- strained project scheduling[J]. Journal Operations Research Soc, 1960,47(5): 678-689. 被引量:1
  • 7Kim K, de la Garza J M. Phantom float[J]. Journal of Con- struetion Engineering and Management, 2003, 129(5): 507-517. 被引量:1
  • 8白思俊.多资源约束的网络计划的启发式优化方法[J].系统工程理论与实践,1996(1):42-47. 被引量:1
  • 9克利福德·格雷,埃里克·拉森.项目管理教程[M].北京:人民邮电出版社,2005. 被引量:1

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部