摘要 随着电力事业的蓬勃发展,新建架空输电线路施工过程中,不可避免需要跨越已运行带电线路,供电公司履行对社会的不停电服务承诺,办理停电十分困难,不停电跨越施工已成为趋势。本文根据新疆与西北主网联网750千伏第二通道线路工程施工5标的跨越施工经验,阐述对常规无跨越架不停电架线施工技术的应用新方法。 Along with the vigorous development of the electric power industry, in new overhead transmission line construction process, it is inevitable to cross electrified hne, power supply company in order to implement the service promise, making power cutting is very difficult, no power cut crossing construction has become a trend. According to the crossing construction experience of Xinjiang and the northwest major network 750KV the second line construction 5 mark, the paper elaborated new application method of conventional no crossing frame no power cut construction technology.
出处 《价值工程》 2013年第32期109-110,共2页 Value Engineering
关键词 输电线路 无跨越架 不停电跨越 新方法 transmission line, non-crossing frame no power cut crossing the new method
  • 相关文献

参考文献7

共引文献16

同被引文献24

引证文献9

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部