摘要
通过象山拦河闸水工模型试验,测试和分析拦河闸(橡胶坝)、冲沙闸的运行流态、流速分布和泄流能力,最终优化拦河闸消能工和电站的布置,改善其运行水力特性。该成果不仅为枢纽工程设计和运行管理提供科学依据,同时对开展同类问题的研究提供参考。
In this study, the hydraulic characteristics of Xiangshan hydraulic complex were experimentally investigat- ed. Flow velocity, flow patterns, velocity distributions and overflow discharge of the rubber dam and the flush sluice were tested and analyzed. The discharge capacity of the barrage and the hydraulic characteristics of the barrage were improved. Moreover, the results can be used for scientific reference in the engineering design and operation management, as well as in the research for similar questions.
出处
《广东水利电力职业技术学院学报》
2013年第3期5-10,共6页
Journal of Guangdong Polytechnic of Water Resources and Electric Engineering
关键词
拦河闸
橡胶坝
冲沙闸
电站
底流消能
arrage
rubber dam
silt-releasing sluice
power station
energy dissipation by underttow