摘要 在某铝土矿山井建平巷开挖掘进施工过程中,碰到一个约60 m宽大断层破碎带,围岩自稳能力差,施工不当就会引起冒顶等垮塌事故,严重影响施工安全和施工进度。采用工作面超前钻探,针对软弱破碎带采用小管棚超前支护可以保证巷道顺利的掘进。详细介绍了该段巷道掘进中管棚支护设计参数与施工要求,工程历经2个多月,顺利通过该破碎带。 During process of roadway drilling,excavation and construction in a bauxite mine,there usually meets with a fracture zone with an approximately 60 m wide fault.Since the surrounding rock has a poor self-stability ability,the improper construction would result in the roof caving and collapse,seriously influence the construction safety and schedule.The paper introduces in detail the design parameters and construction requirements of pile-shed supporting during the roadway tunneling.After experiencing over two months in this project,the tunnel successfully passed this fracture zone.The advance drilling at working face is adopted.Especially in the weak fracture zone,the small pile-shed supporting can ensure the roadway tunneling.
作者 付宗智 曹平
出处 《金属矿山》 CAS 北大核心 2013年第6期9-12,共4页 Metal Mine
关键词 铝土矿 超前钻探 管棚支护 喷射混凝土 Bauxite mine Advance drilling Pile-shed supporting Shotcrete
  • 相关文献

参考文献6

  • 1关宝树编著..隧道工程施工要点集[M].北京:人民交通出版社,2003:462.
  • 2GB50511-2010煤炭井巷工程施工规范[S].北京:中国煤炭建设协会,2010. 被引量:1
  • 3YSJ021-93有色金属矿山井巷工程设计规范[S].北京:北京有色冶金设计研究总院,1993. 被引量:2
  • 4GB50086-2001.锚杆喷射混凝土支护技术规范[S].[S].,2001.. 被引量:274
  • 5GB50010--2010混凝土结构设计规范[S].北京:中国建筑工业出版社,2010. 被引量:30
  • 6MTT632-1996井下探放水技术规范[S].北京:煤炭工业部,1996. 被引量:1

共引文献302

同被引文献11

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部