通过参与衡阳市衡州大道(红湘路至蒸阳路)工程铁路货场跨线桥施工中钢箱梁吊装施工,分析了工程的风险和具体吊装过程,可为同类型的钢箱梁施工提供有益的探索和借鉴.
According to the Hampshire road in Hengyang City (Red Hunan Road to Steamed Yang Road) engineering railway overpass bridge construction of steel box girder hoisting construction experience, the author provides a useful exploration and experience of project risks and specific installation process for the steel box girder construction of the same type.
出处
《湖南城市学院学报(自然科学版)》
CAS
2013年第2期24-27,共4页
Journal of Hunan City University:Natural Science
关键词
跨铁路
临时支墩
钢箱梁吊装
施工控制技术
cross the railway
temporary pier
steel box girder erection
construction control technology