斜拉桥施工初始索力的确定 被引量:16

THE DETERMINATION OF THE INITLAL CABLE FORCES FOR CABLE-STAYED BRIDGES
下载PDF
导出
摘要 本文介绍了直接利用前进分析确定斜拉桥施工初始索力的方法。该方法以施工正序进行分析,能够精确计及结构的几何非线性、混凝土收缩徐变以及其他因素的影响。与以往随方法相比,该方法考虑因素全面,计算简使、精度高。用该方法获得的施工初始索力进行施工,成桥索力及线型易于保证,可以大大减少工程控制的工作量,节约大量人力、物力和财力。 This apaer is concerned with the deermination of the initial cable forces of cable stayed bridges. A forward-analysis method is introduced , in which the actural construction process is considered . The influences of geometric nonlinearity , shrinkage and creep of concrete are taken into account. It is shown that the method is more comprehensive , easier and more accurate than previous methods . With the initial cable forec determined by the present method , the final cable force and shape can be determined easily . Consequently ,the workload of construction control human ,material and financial resources are reduced substantially . A program based on the method is devloped The P-K cable-stayed bridge of America has been analyzed .
出处 《工程力学》 EI CSCD 北大核心 2000年第3期121-126,共6页 Engineering Mechanics
关键词 斜拉桥 初始索力 施工 cable-stayed bridge,the imitial cable forces
  • 相关文献

参考文献1

共引文献9

同被引文献53

引证文献16

二级引证文献34

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部