期刊文献+

整体悬挂式烟囱钢内筒退锚换点液压提升技术

Backing Anchors with Shift-point Hydraulic Lifting Construction of Integral Suspended Chimney Steel Liner
下载PDF
导出
摘要 结合印尼某电厂烟囱钢内筒施工,以一次穿线退锚换点原理为重点,介绍整体悬挂式钢内筒退锚换点法液压提升施工技术及工艺,主要包括螺旋退锚调节器结构构造及应用、提升换点系统组成、液压千斤顶受力支承点与原设计结构荷载等同布置原则及钢绞线周转利用技术。退锚换点提升技术具有简化工序、换点安全可靠、减少高空作业、降低钢绞线消耗等优点,是对液压提升工艺的进一步改进和优化。 Combined with an Indonesian power plant's chimney steel liner installation and taken the principle of backing anchors with shift-point as a key,the presentation of integral suspended steel liner backing anchors with shift-point hydraulic lifting construction and process is introduced,which mainly consists of spiral backing anchors regulator structure and application,lifting shift-point system,hydraulic jack bearing supporting point and original design load equivalence arrangement principle and strand turnover utilization techniques.Backing anchors with shift-point lifting technique have some advantages,such as simple process,shifting point securely and reliably,decreasing high attitude operation,and reducing strand consumption etc.,which is a further improvement and optimization of hydraulic lifting technique.
作者 牛昌林 崔清
出处 《施工技术》 CAS 北大核心 2013年第2期38-41,共4页 Construction Technology
关键词 钢结构 烟囱 钢内筒 退锚换点 液压提升 施工技术 steel structures chimney steel liner backing anchors with shift-point hydraulic lifting construction
  • 相关文献

参考文献7

二级参考文献17

共引文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部