摘要 针对带有并行机与批处理机的混合流水车间调度问题,提出一种基于"鼓—缓冲器—绳子"—遗传算法的调度方法。首先建立了识别瓶颈工作站的步骤,开发了相应的启发式算法,进行了问题初始解的求解,在此基础上应用改进遗传算法对作业在瓶颈工作站上的加工顺序进行优化,并利用缓冲机制决定了作业的投放策略,同时对非瓶颈设备运用优先级规则进行了作业的排程。最后通过算例实验和性能分析,验证了所提调度方法的有效性与实用性。 Aiming at the Hybrid Flow Shop( HFS) problems with batch processing machines and identical equipment, a scheduling method based on Drum-Buffer-Rope(DBR)and Genetic Algorithm(GA)was proposed. The steps were established to identify the bottleneck workstation and relevant heuristic algorithm was developed to generate the ini- tial solutions. On this basis, the processing sequence of bottleneck workstation was optimized by using an improved GA. The policy of job-release was determined with buffering mechanism, and priority rules were used to scheduling operation of non-bottleneck workstations. Through examples and performance analysis, the effectiveness and feasi- bility of proposed scheduling method were verified.
作者 项洁 周炳海
出处 《计算机集成制造系统》 EI CSCD 北大核心 2012年第11期2485-2491,共7页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(71071115 61273035) 国家863计划资助项目(2009AA043000)~~
关键词 混合流水车间 调度 鼓-缓冲器-绳子 瓶颈 启发式算法 优先级规则 hybrid flow shop scheduling drum-buffer-rope bottleneck heuristic algorithms priority rules
  • 相关文献

参考文献10

  • 1GUPTA J N D. Two-stage hybrid flow shop scheduling prob- lem[J]. Operational Researeh Society, 1988,39(4):359-364. 被引量:1
  • 2HUNSUCKER J L, SHAH J R. Comparative performance analysis of priority rules in a constrained flow shop with multi- ple processor environment[J]. European Journal of Operation- al Research,1994,72(1) : 102-104. 被引量:1
  • 3BELLANGER A, OULAMARA A. Scheduling hybrid flow shop with parallel batehing machines and eompatibilities[J]. Computers & Operations Research, 2009,36(6) :1982-1992. 被引量:1
  • 4TANG Lixin, WANG Xianpeng. An improved particle swarm optimization algorithm for the hybrid flowshop scheduling to minimize total weighted completion time in process industry [J]. IEEE Transactions on Control Systems Technology, 2010,18(6) : 1303-1314. 被引量:1
  • 5ONWUBOLU G C, MUTINGI M. A genetic algorithm ap- proach to the theory of constraints product mix problems[J]. Production Planning & Control, 2001,12 (1) : 21-27. 被引量:1
  • 6LI Lin, HUO Jiazhen, TANG Ou. A hybrid flowshop schedu- ling problem for a cold treating process in seamless steel tube production[J]. International Journal of Production Research, 2011,49(15) :4679-4700. 被引量:1
  • 7SIRIKRAI V, YENRADEE P. Modified Cnmrbuffer-mpe sched- uling mechanism for a non-identical parallel machine flow shop with processing-time variation[J]. International Journal of Production Research, 2006,44(7) : 3509-3531. 被引量:1
  • 8郭永辉,钱省三.基于鼓-缓冲器-绳子理论的整合式生产作业控制系统研究[J].计算机集成制造系统,2006,12(2):252-256. 被引量:10
  • 9CAMPBELL H G, DUDEK R A, SMITH M L. A heuristic algorithm for the n-job m-machine sequencing problem[J]. Management Science, 1970,16(5) : 630-637. 被引量:1
  • 10PALMER D S. Sequencing jobs through a multi-stage process in the minimum total timr-a quick method of obtaining a near optimum[J]. Operations Research Quarterly, 1965, 16 (1) :101-107. 被引量:1

二级参考文献13

  • 1SCHRODER R G,ANDERSON J C,TUPY S E,et al.A studyof MRP benefits and costs[J].Journal of Operations Management,1981,2(1):1-9. 被引量:1
  • 2GOLDRATT E M,COX J.Theory of constraints[M].Croton -on-Hudson,NY,USA:North River Press,1990. 被引量:1
  • 3GARDINER S C,BLACKSTONE J H,GARDINER L R.The evolution of the theory of constraints[J].Industrial Management,1994,36(3) :13-16. 被引量:1
  • 4COOK D P.A simulation comparison of traditional,JIT andTOC manufacturing system in a flow shop with bottlenecks[J].Production and Inventory Management Journal,1994,35 (1):73-78. 被引量:1
  • 5MILTENBURG J.Comparing JIT,MRP and TOC and embedding TOC into MRP[J].International Journal of ProductionResearch,1997,33 (4):1147 - 1169. 被引量:1
  • 6BLACKSTONE J H,GARDINER L R,GARDINER S C.Aframework for the systemic control of organizations[J].International Journal of Production Research,1997,35 (3):597605. 被引量:1
  • 7MILLER B.Applying TOC in the real world[J].ⅡE Solution,2000,32(5) :49-55. 被引量:1
  • 8SCHRAGEHEIM E,RONEN B.Drum- Buffer- Rope shop floor control[J].Production and Inventory Management Journal,1990,(third quarter):18-22. 被引量:1
  • 9RONEN B,STARR M K.Synchronized manufacturing as in OPT:from practice to theory[J].Computers Industrial Engineering,1990,18(4):585-600. 被引量:1
  • 10SCHRAGENHEIM E,RONEN B.Buffer management:a diagnostic tool for production control[J].Production and Inventory Management Journal,1991,2(2) :74-79. 被引量:1

共引文献9

同被引文献37

引证文献4

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部