针对船舶平面分段流水线生产中存在的计划不准确、调度滞后、生产效率低等问题,分析平面分段流水线的特点,提出一类非完全混合流水线调度模型,并对该类调度问题进行优化研究。同时,综合考虑非完全混合流水线调度问题的特殊性及船舶建造的复杂性,以分段最大完工时间最小化为优化目标,建立两阶段的非线性整数规划模型,并利用分支定界法优化求解。结合某船厂实际数据进行实例验证和多次数值实验,并与混合遗传算法进行对比。结果表明,该模型和算法能有效解决平面分段流水线调度中存在的问题。
The property of panel block line was analyzed and a new model called non-completely hybrid flow line was developed based on the research of the panel block scheduling problems including inaccurate planning, lagged sched- uling and ineffectiveness. Moreover, by considering both the uniqueness of non--completely hybrid flow line sched- uling problem and the complexity of shipbuilding, a two stage of nonlinear integer programming model with minimi- zing of maximum completion time section as optimization objective. And the model's optimal solution was solved by the branch and bound method. Finally, application data obtained from a shipyard was used to validate the model and carry out series of numerical experiments. The result indicated that the model and arithmetic proposed was an effec- tive method to resolve the scheduling problems existing in panel block line.
出处
《计算机集成制造系统》
EI
CSCD
北大核心
2012年第11期2435-2445,共11页
Computer Integrated Manufacturing Systems
基金
国家自然科学基金资助项目(70872076)
上海科技创新行动计划资助项目(11dz1121803)~~
关键词
非完全混合
流水线
平面分段
调度
分支定界法
non-completely hybrid
flow line
panel block
scheduling