摘要 针对船舶平面分段流水线生产中存在的计划不准确、调度滞后、生产效率低等问题,分析平面分段流水线的特点,提出一类非完全混合流水线调度模型,并对该类调度问题进行优化研究。同时,综合考虑非完全混合流水线调度问题的特殊性及船舶建造的复杂性,以分段最大完工时间最小化为优化目标,建立两阶段的非线性整数规划模型,并利用分支定界法优化求解。结合某船厂实际数据进行实例验证和多次数值实验,并与混合遗传算法进行对比。结果表明,该模型和算法能有效解决平面分段流水线调度中存在的问题。 The property of panel block line was analyzed and a new model called non-completely hybrid flow line was developed based on the research of the panel block scheduling problems including inaccurate planning, lagged sched- uling and ineffectiveness. Moreover, by considering both the uniqueness of non--completely hybrid flow line sched- uling problem and the complexity of shipbuilding, a two stage of nonlinear integer programming model with minimi- zing of maximum completion time section as optimization objective. And the model's optimal solution was solved by the branch and bound method. Finally, application data obtained from a shipyard was used to validate the model and carry out series of numerical experiments. The result indicated that the model and arithmetic proposed was an effec- tive method to resolve the scheduling problems existing in panel block line.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2012年第11期2435-2445,共11页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(70872076) 上海科技创新行动计划资助项目(11dz1121803)~~
关键词 非完全混合 流水线 平面分段 调度 分支定界法 non-completely hybrid flow line panel block scheduling branch and bound method
  • 相关文献

参考文献18

  • 1张志英,李川,李珍.面向船体曲面分段建造的虚拟流水线生产调度[J].工业工程,2010,13(1):58-63. 被引量:11
  • 2刘琳,谷寒雨,席裕庚.工件到达时间未知的动态车间滚动重调度[J].机械工程学报,2008,44(5):68-75. 被引量:17
  • 3KARIMI N, ZANDIEH M, KAR-AMOOZ R. Bi-objective group scheduling in hybrid flexible flowshop: a multi-phase ap- proach[J]. Expert Systems with Applications, 2009, 37 (6) : 4024-4032. 被引量:1
  • 4YAGMAHAN B, YENISEY M M. Ant colony optimization for multi-objective flowshop scheduling problem[J]. Comput- ers b-Industrial Engineering, 2008, 54(3) :411-420. 被引量:1
  • 5GAJPAL Y,RAJENDRAN C,ZIEGLER H. An ant colony al- gorithm for scheduling in flowshops with sequence-dependent setup times of jobs [J]. International Journal of Advanced Manufacturing Technology, 2006, 30(5/6) :416-424. 被引量:1
  • 6ALEXANDROS D C, CHRISSOLEON P T. Exact analysis of a two-workstation one-buffer flow line with parallel unreliable machines [J]. European Journal of Operational Research, 2009,197(2) : 572-580. 被引量:1
  • 7OMAR M K, TEO S C, YASOTHEI S. Mixed integer pro- gramming formulation for hybrid flow shop scheduling problem [C]//Proceedings of the 2010 IEEE Conference on IEEM. Washington,D. C. ,USA:IEEE,2010:385-389. 被引量:1
  • 8王凌,周刚,许烨,金以慧.混合流水线调度研究进展[J].化工自动化及仪表,2011,38(1):1-8. 被引量:27
  • 9CHEN C L, CHEN C L. A bottleneck-based heuristic for minimizing makespan in a flexible flow line with unrelated par- allel machines [J]. Computers & Operations Research, 2009, 36(11) ~3073-3081. 被引量:1
  • 10TAVAKKOLI-MOGHADDAM R, SAFAEI N R,SASSANI F. A memetic algorithm for the flexible flow line scheduling problem with processor blocking[J]. Computers & Opera- tions Research, 2009, 36(2).. 402-414. 被引量:1

二级参考文献140

共引文献72

同被引文献44

  • 1龙凡.面向对象设计和面向对象编程[J].电信科学,1995,11(3):57-61. 被引量:2
  • 2左燕,谷寒雨,席裕庚.大规模流水线调度的瓶颈分解算法研究[J].控制与决策,2006,21(4):425-429. 被引量:10
  • 3王敏,邵定宏,陆金桂.动态链接库技术及其应用实例[J].微计算机信息,2006,22(09X):272-274. 被引量:16
  • 4李宁.船舶制造平面分段流水线作业优化应用与研究[D].上海:上海交通大学,2006. 被引量:2
  • 5刘心报,郭盈,程浩.一种基于NEH算法的有效求解半flowshop问题的迭代插入算法[J].仪器仪表学报,2009,30(增刊):395-399. 被引量:3
  • 6WANG L,ZHANG L, ZHENG D Z. An effective hybrid ge- netic algorithm for flow shop scheduling with limited buffers [J]. Computers and Operations Research, 2005, 33: 2960- 2971. 被引量:1
  • 7HEJAZI R, SAGHAFIAN S. Flowshop scheduling probl- ems with makespan criterion: a review [ J ]. International Journal of Production Research, 2005, 43 : 2895-2929. 被引量:1
  • 8LIU Shiqiang, ERHAN K. Scheduling a flow shop with com- bined buffer conditions [ J ]. Int J Production Economics, 2009, 117:371-380. 被引量:1
  • 9TAILLARD E. Some efficient heuristic methods for the flow shop sequencing problem [ J ]. European Journal of Opera- tional Research, 1990, 47(1) :65-74. 被引量:1
  • 10WANG X, TANG L. A tabu search heuristic for the hybrid flowshop scheduling with finite intermediate buffers [ J ]. Computers and Operations Research, 2009,36 : 907-918. 被引量:1

引证文献5

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部