:中国人民保险公司山西省分公司高层住宅楼施工中 ,通过方案比较 ,改用了导轨式爬架 ,与原外脚手架封闭方案相比 ,节约钢材及辅料60%以上 ,节约投资40%以上。同时减轻了工人劳动强度 ,节约脚手架的搭设费用 ,增加施工的安全性 。
In the construction of high-rise dwelling of Chinese People Insurance Corporation,Shanxi Branch, originally planed external scaffolding enclosure system was finally replaced by rail climbing scaffolding system.Through a scheme comparison,the rail climbing system may save steel and auxiliary material by 60% and investment by 40% to the former. In addition, labour intensity and scaffolding erection cost was decreased,while construction safety and efficiency was improved.
出处
《建筑技术》
北大核心
2000年第8期530-532,共3页
Architecture Technology
关键词
高层住宅
导热式爬架
安装
提升
high-rise dwelling
rail climbing scaffolding
erection
raising