齿轮座是轧钢厂各种轧机的传动装置,承担很大的传动荷载。齿轮座各部件在制造加工完成后都要进行预装、形成齿轮座整体设备,达到安装条件。针对轧钢厂各种轧机传动齿轮座预装工作的难点,通过对预装过程进行认真剖析研究,找出其中的影响因素和薄弱环节,制定出了拉杆螺栓的热装、齿轮轴及轴承的预装、粗刮轴承、精刮轴承的工艺措施。使齿轮座的垂直度、水平度、齿轮啮合、各部位间隙、紧力都达到国家标准。使齿轮座达到整体安装的技术要求。
The gear seat is the transmission of all kinds of rolling mils, Take a lot of transmission load. A single piece of equipment in the gear processing after finish to form a whole preinstalled, gear equipment to installation conditions. According to different rolling rolling mills gear pre-installed a difficult, through the process analysis research seriously preinstalled, find out the influence factors and the weak link, develop a thermal loading of the rod bolts, gear shafts and bearings pre-installed, rough scraping bearings, precision scraping bearing process measures, verticality and horizontality of the gear seat, gear meshing, the various parts of the gap, the tightening force to meet the national standard.Gear seat a whole installation of the technical requirements.
出处
《机械》
2012年第7期71-74,共4页
Machinery
关键词
齿轮座
拉杆螺栓
水平度
垂直度
热装温度
各部位间隙调整
gear xeat
stay bolt
levelness
verticality
hot charging temperature
clearance of each part