2013年江西电网将建设1 000 kV南昌特高压站,以电网规划设计为基础,以电网建设项目进度为条件,对特高压入赣前、后江西电网的短路电流进行详细计算分析,在此基础上分析了特高压对江西电网短路电流的影响,并提出了降低江西电网短路电流和保障电网安全稳定运行的措施和建议。
In 2013,the 1 000 kV Nanchang ultra high voltage(Hereinafter referred to as UHV) station will be constructed in Jiangxi power grid.This paper compares the short circuit current calculation of Jiangxi power grid without the UHV to within the UHV in detail based on network planning design and the power grid construction project schedule.At last,this paper analyzes the effect of the UHV on short circuit current in Jiangxi power grid,then put forward some measures and suggestions to reduce the short circuit current in Jiangxi power grid and guarantee the safety and steady of power network's operation.
出处
《江西电力》
2012年第1期10-13,共4页
Jiangxi Electric Power
关键词
江西电网
特高压
短路电流
计算分析
Jiangxi power grid
ultra high voltage
short circuit current
calculation and analysis