现浇混凝土模板侧压力研究 被引量:13

Study of Lateral Pressure of Cast-in-place Concrete Formwork
下载PDF
导出
摘要 通过在某桥墩模板内侧埋设压力盒进行墩身混凝土的侧压力监测,发现随着混凝土的浇注,对应测点压力迅速上升,达到峰值后减小,然后保持不变;各测点形成最大侧压力耗时7.6~12.8h;实测最大侧压力为规范计算值的1.01~2.2倍。结合实测数据,在分析国内、外有关侧压力计算公式之后,偏于安全考虑,建议修订公路规范中模板侧压力计算公式。 The lateral pressure of pier shaft concrete of a bridge was monitored by burying pressure box in the pier formwork. It is found that the pressure of the corresponding testing point rapidly rises as the concrete is casted, decreases after reaching its crest value, and then keeps constant. 7.6~12.8 h had been consumed when greatest lateral pressure appeared in all the tes- ting points. The measured greatest lateral pressure is 1.01-2.2 times of that recorded in the code. Based on the measured data and the analysis of the lateral pressure calculation formula at home and abroad, and out of the consideration of safety, it is suggested that the calculation formulae of formwork lateral pressure in the Highway Code should be revised.
作者 汪水清 刘方
出处 《世界桥梁》 北大核心 2012年第2期42-45,共4页 World Bridges
关键词 现浇混凝土 模板 侧压力 研究 cast-in-place concrete formwork lateral pressure study
  • 相关文献

参考文献5

二级参考文献7

共引文献1740

同被引文献60

引证文献13

二级引证文献45

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部