高压直流输电开路试验中换流阀设备保护的探讨 被引量:13

Case Study on Converter Valve Protection in Open-circuit Test
下载PDF
导出
摘要 在呼伦贝尔至辽宁直流输电工程换流阀直流开路试验中,由于换流阀多次保护触发动作引起系统跳闸,导致站系统试验无法进行。笔者结合该试验过程,从直流开路试验基本原理、换流阀监控和极控制保护几个方面进行分析讨论,提出阀控单元(VCU)对换流阀的保护完全可以保证换流阀设备的安全,极控制保护对换流阀保护触发动作的监控可只作为监视,不必产生系统跳闸,从而保证OLT试验顺利进行。 In the open-circuit test of converter valve in Hulunbeier to Liaoning HVDC transmission project,the sub-system test was interrupted because of frequent tripping operations due to protection of converter vale.In this paper,the basic principle of open-circuit test,and the converter valve monitoring and pole control protection in the test are analyzed,and conclusions are drawn that VCU protection of converter valve is sufficient,and the pole control system should merely monitor the triggering action of converter valve protection instead of lead to system tripping,which may let the open-circuit test be performed successfully.
作者 李侠 陈干
出处 《高压电器》 CAS CSCD 北大核心 2012年第3期86-89,共4页 High Voltage Apparatus
关键词 OLT试验 换流阀 VCU 保护触发 open line test(OLT) converter valve valve control unit(VCU) protection triggering
  • 相关文献

参考文献13

二级参考文献71

共引文献158

同被引文献112

引证文献13

二级引证文献48

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部