摘要
就双代号施工网络计划优化管理问题,研究了次关键路线上非关键工序的寻求方法,给出了图上计算和解析表达的求解过程,方便了网络计划的优化和管理。
This article studies about how to look for the noncritical proves in secondary critical path planing about the optimum manage- ment of the double-cord construction network planing provides the calculation on the drawing and the solve of the analysis and makes it convenient for the optimum network planing and management.
出处
《燕山大学学报》
CAS
2000年第1期40-42,共3页
Journal of Yanshan University