摘要
介绍了某船台滑道工程采用钢护筒干法施工水下桩帽,利用导杆法精确控制水下滑道"井"字形轨道梁安装位置的具体做法及相关体会。
This paper introduced the dry construction process by application of steel casing to install pile cap underwater. As well, with help of guide-bar, the method and experience of how to control the position of well-shaped track beams of slipway of berth accurately were presented here.
出处
《大坝与安全》
2011年第6期29-36,共8页
Dam & Safety
关键词
水下桩帽
干法施工
导杆
under-water pile cap
dry construction
guide-bar