期刊文献+

锦屏一级高拱坝断层模拟处理与分析 被引量:2

Simulation Processing and Analysis of Faults of Jinping First-stage High Arch Dam
下载PDF
导出
摘要 本文对锦屏一级高拱坝左右岸存在的f2、f5、f13、f14等断层进行了模拟混凝土置换处理,应用三维有限元法计算了坝体和基础的位移,经比较分析可知,对f5和f13断层同时进行处理可使坝体和基础的顺河向位移最小,横河向位移更为对称,并减小拱坝整体向右岸的位移。 The treatment of concrete replacement of the faults f2,f5,f13,f14 which exist in both banks of Jinping first-stage high arch dam is simulated.Three-dimensional FEM is applied to calculate the displacement of the dam and foundation.The conclusion can be drawn from the comparative analysis that if f5 and f13 faults are processed simultaneously,the displacement of the dam and the foundation down a river will be the smallest,the displacement across a river will be more symmetrical,and it can reduce the displacement to the right bank as a whole.
作者 宋鹏 傅辉云
出处 《水电能源科学》 北大核心 2012年第2期103-105,共3页 Water Resources and Power
基金 国家自然科学基金资助项目(51079046 50909041 50809025 50879024) 江苏省"333高层次人才培养工程"基金资助项目(2017-B08037) 江苏省普通高校研究生科研创新计划基金资助项目(CX09B_163Z)
关键词 拱坝 断层 处理 有限元 位移 arch dam fault treatment finite element method displacement
  • 相关文献

参考文献4

  • 1国家电力公司成都勘察设计研究院.雅砻江锦屏一级水电站可行性研究报告[R].成都:国家电力公司成都勘察设计研究院,2003. 被引量:2
  • 2沈长松等..水工建筑物[M].北京:中国水利水电出版社,2008:616.
  • 3何江达,林正伟,王启智.锦屏一级高拱坝结构特性及坝肩稳定性研究[J].四川大学学报(工程科学版),2004,36(2):12-16. 被引量:14
  • 4陈火红等编著..新编Marc有限元实例教程[M].北京:机械工业出版社,2007:463.

二级参考文献3

共引文献14

同被引文献18

引证文献2

相关作者