摘要
针对唐河水电站面板堆石坝填筑设计标准,分析了混凝土面板堆石坝布置与设计,通过现场碾压试验,取得了大坝填筑施工工艺及参数,从而为水电站大坝主堆石区填筑施工提供指导。
According to the design standard of the filling design of the faced rock-fill dam of Tanghe hydraulic power plant,the paper analyzes the allocation and design of the concrete faced rock-fill dam,according to the rolling test,achieves the construction craft and parameter of the dam's filling,so as to provide the direction for the filling construction of the main faced rock-fill dam of the hydraulic power plants.
出处
《山西建筑》
2011年第32期207-208,共2页
Shanxi Architecture
关键词
主堆石
碾压参数
施工工艺
水电站
main stacking rock
rolling parameter
construction craft
hydraulic power plant